In some of the last posts, we have talked about the work at the Swann House site. The team has been clearing brush and exposing the foundation walls. We have photographed and documented our work and will be out again tomorrow to expose a bit more of the foundation and do some detailed drawings. In the meantime, I digitized a sketch that Jim drew in the field. It is not to scale but should give the reader (that's you!) a better look at the building footprint as we see it today.
-The North wall appears to be the most severely damaged at the exposed level.
Once we have finished exposing and drawing the foundation, I will post a more complete and accurate drawing.
- Peter
No comments:
Post a Comment